Steps to a revitalized Surrey Memorial Hospital

Bookmark and Share
The following milestones are set for the Surrey Memorial Hospital Expansion and Redevelopment project:
  • 2009  Phase 1 Request for Qualifications issued
  • February 2010  Phase 1 Request for Proposals is issued
  • 2010 Builder is selected
  • 2011 Construction begins
  • 2013 New emergency department is expected to open
  • 2014 Renovations and new Critical Care Tower is complete

Latest news

Keep up to date on the project:

March 2011 -  Premier launches B.C.’s largest-ever health-care project

October 2010 - Surrey Memorial Hospital expansion moves ahead

December 2009 - Three teams short-listed for Surrey Memorial Hospital Expansion

Renal unit expansion complete

The renal expansion project was a $10 million initiative which began in August 2007 and is now complete. The newly expanded 30-station renal unit includes space for 12 new renal stations and an expanded waiting area to accommodate patients as they wait for dialysis. 

Intensive care unit expansion complete

The expansion of the Surrey Memorial Hospital intensive care unit (ICU) to 15 beds was a complex three-phase capital project.  It involved expanding the intensive care unit  by three beds and renovating and relocating several other programs within the hospital. Due to the sensitive nature of the ICU environment the project was carefully staged to ensure patient safety. Construction of the ICU and the new renal unit occurred simultaneously.